Skolkovo Institute of Science and Technology

Customer:Skolkovo Institute of Science and Technology
Implementation period:2016-2017
Object location:Skolkovo Innovation Center, Moscow
Project:Creation of a laboratory complex of nano-satellites of the Skoltech Space Center, a big biodata laboratory of the Skoltech center for systemic biotechnology and biomedicine, a plasmonics complex of the Skoltech Center for Photonics and Quantum materials, a Skoltech pultrusion laboratory of the Skoltech Center for Design, Production Technologies and Materials
Project features:

Designed facility area: 900 m2

 

Cleanroom area: 150 m2

 

Cleanness class: 7-8ISO

R-Technologies acted as a General Designer and General Contractor. We developed the detailed design and then built the laboratory complex in accordance with it.

The pultrusion laboratory is intended for the following researches:

• Study of materials and development of technologies for manufacturing the pultruded profiles from thermoset materials

• Study of materials and development of technologies for manufacturing the pultruded profiles from thermoplastics.

• Carrying out laboratory work on a pultruder installation for teaching students.

• Fulfillment of commercial orders for pultruded profiles.

 

The Plasmonics Laboratory of the Skoltech Center for Photonics and Quantum Materials makes research work for the creation and research of plasmon structures and meta materials based on them for applications in biomedicine and nanoelectronics.

 

The following researches are carried out in the big bio-data laboratory:

• standard experiments for the extraction of DNA, RNA, proteins, metabolites and lipids from biological samples such as human and farm animals body tissues and plants.

• highly efficient sequencing of nucleic acids (DNA or RNA).

• mass spectrometry in combination with liquid chromatography for highly efficient analysis of metabolites and lipids.

 

The nano-satellites laboratory is creating nano-satellites.

 

The plasmonic laboratory has a cleanroom for electronic lithography and optics. Cleanrooms were built with using the M-Tech  elements, the Filter JSC suspended ceilings.

 

For the laboratory complex, independent make-up air supply systems, precision microclimate systems in service rooms, technological exhaust systems, a chilled water supply system, a compressed dry air supply system, a power supply system, facility monitoring and control system were implemented.

The project implementation, including design, construction and commissioning, took only six months.